【正文】
SC = Software coder(2) How many of each type of resource will need to be recruited for the project as a whole if the earliest finish date is to be preserved?(Suppose each activity is carried out by only one staff)(3) What impact would there be on the project if there were only one systems designer?(4) What impact would there be on the project if there were only one systems designer and one coder?8.Answer:9.Answer:。1. List the problems you experienced when you carried out a recent ICTrelated assignment. Try to put these problems into some order of magnitude. For each problem consider whether there was some way in which the problem could have been reduced by better organization and planning by yourself.2. We plan to invest 5000$ for a project and wish to get 12500$ profit after five years