【正文】
Review Report PI Note (maybe Email) Requirement Matrix Draft Project Plan Client Engagement Exit Criteria ? Notification from Product management team stating development work can starts for PLM projects ? Contract Review report with an acceptance or rejection decision for nonPLM contract. Project Planning Entry Criteria ? PM or DM is trained in the area of software project management and software estimating. ? Contract review pleted and project initiation note raised Project Planning Inputs ? MRD, System Requirement, and part of UC, UI etc. ? SOW (if any) ? Estimation Results Project Planning Activities 1 PM or appoints DM prepares a draft project plan, as per defined template, based on SOW/ contract review record/ contract/ MRD and other information available。 2 Depending on project needs and technical features, PM and DM define the software life cycle。 To be Continued… Project Planning Activities 3 Based on SOW and MRD, System Requirement, UC, etc, PM establishes WBS (MS Project)。 4 PM estimates the size, plexity, eff