【正文】
當(dāng)然,這次課題能順利的完成,還要感謝一位重要的人,我的畢業(yè)指導(dǎo)老師葉華老師。具體到施工用電組織設(shè)計,認(rèn)真做到用電設(shè)施、設(shè)備的負(fù)荷計算,線纜、開關(guān)、漏電保護(hù)器的合理選取,防雷、防火、安全用電措施和規(guī)范的編寫,施工圖的設(shè)計以及預(yù)算書的編制,及完善臨時用電安全技術(shù)檔案等。 施工圖預(yù)算是在施工圖設(shè)計完成后,工程開工前,根據(jù)已批準(zhǔn)的施工圖樣、現(xiàn)行的預(yù)算定額、費(fèi)用定額等,在施工方案或施工組織設(shè)計已大致確定的前提下,確定單位工程造價的技術(shù)經(jīng)濟(jì)文件。 (3)電氣設(shè)備要嚴(yán)格按其性能運(yùn)行,不準(zhǔn)超載運(yùn)行,須知好經(jīng)常性的檢修保養(yǎng)使設(shè)備能正常運(yùn)行,并保持通風(fēng)良好。 (7)建立安全檢查和評估制度。 (3)建立技術(shù)交底制度。總箱、分配電箱必須有重復(fù)接地。單相回路內(nèi)的照明開關(guān)箱必須裝設(shè)漏電保護(hù)器。對配電箱,開關(guān)箱進(jìn)行檢查、維修時,必須將其前一級相應(yīng)的電源開頭分閘斷電,并懸掛停電標(biāo)志牌,嚴(yán)禁帶電作業(yè)。熔絲應(yīng)和用電設(shè)備的實(shí)際負(fù)荷相匹配,熔斷器的熔體(保險絲)更換時,嚴(yán)禁用不符合原規(guī)格的熔體或金屬裸線代替使用?!?,移動式開關(guān)箱應(yīng)裝高在堅固的支架上,~。漏電保護(hù)裝置裝設(shè)位置、型式與主要特性參數(shù)選擇必須適應(yīng)施工現(xiàn)場的實(shí)際需要,達(dá)到二級保護(hù)。移動用電設(shè)備必須切斷電源,在一般情況下不許帶電作業(yè),帶電作業(yè)要設(shè)監(jiān)護(hù)人。 (1)施工現(xiàn)場臨時用電實(shí)行三相五線制、三級配電兩級保護(hù)和一機(jī)一閘一保險一箱的做法,嚴(yán)禁用一個電器開關(guān)直接控制二臺及二臺以上用電設(shè)備。采用TN系統(tǒng)做保護(hù)接零時,工作零線(N線)必須通過總漏電保護(hù)器,保護(hù)零線(PE線)必須由電源進(jìn)線零線重復(fù)接地處或總漏電保護(hù)器電源側(cè)零線處,引出形成局部TNS接零保護(hù)系統(tǒng)()。保護(hù)接零(地)有多種系統(tǒng),根據(jù)現(xiàn)行國家標(biāo)準(zhǔn),施工現(xiàn)場專用供電系統(tǒng)必須采用TNS接零系統(tǒng)。否則,應(yīng)予清除或做防護(hù)處理。為了防止火災(zāi),不得使用木板等易燃材料制作。變壓器平均功率因數(shù):,按要求需要對其進(jìn)行補(bǔ)償,采用并聯(lián)電容人工補(bǔ)償?shù)姆绞剑a(bǔ)償容量按公式計算,式中為平均有功負(fù)荷,在此可取其值等于有功計算負(fù)荷;為補(bǔ)償前平均功率因數(shù)角的正切值;為補(bǔ)償后平均功率因數(shù)角的正切值。式中為設(shè)備功率因數(shù)對應(yīng)的正切值。積極學(xué)習(xí)和總結(jié)生產(chǎn)經(jīng)驗(yàn),增強(qiáng)自身專業(yè)技能;加強(qiáng)行業(yè)潛在不安全問題的了解、探索與總結(jié),在思想上樹立積極預(yù)防,建立放心施工的良好工作態(tài)度。 辦公區(qū)、作業(yè)區(qū)、倉庫等場所內(nèi)部應(yīng)整潔有序,生活區(qū)中食堂、供排水、浴室、宿舍應(yīng)符合防火、衛(wèi)生、通風(fēng)、照明等要求。員工技能培訓(xùn),專業(yè)技能人才的引進(jìn)等。 1)認(rèn)真落實(shí)國家各項(xiàng)標(biāo)準(zhǔn)要求,并能夠根據(jù)自身實(shí)際制定企業(yè)內(nèi)部標(biāo)準(zhǔn)管理措施。國家、政府及各級政府機(jī)關(guān)充分發(fā)揮其行政職能對建筑企業(yè)進(jìn)行監(jiān)督與強(qiáng)制管理。部分施工現(xiàn)場項(xiàng)目部安全管理人員,偏重于現(xiàn)場安全設(shè)施,使臨時用電的管理責(zé)任與現(xiàn)場電工為同一人,自己施工、自己檢查、自己驗(yàn)收,造成現(xiàn)場用電在敷設(shè)、安裝、檢查、驗(yàn)收等環(huán)節(jié)處于失控狀態(tài)。由于體制上的不完善和管理上的滯后,大量既沒有進(jìn)行勞動技能培訓(xùn)又缺乏施工現(xiàn)場安全教育的務(wù)工者上崗后,對現(xiàn)場的不安全因素一無所知,對安全生產(chǎn)的重要性沒有足夠認(rèn)識、缺乏規(guī)范作業(yè)的知識,往往由于其本人的不安全行為給予自己或與其相關(guān)作業(yè)環(huán)境下的其他操作人員帶來難以預(yù)料的傷害事故。當(dāng)前建筑市場中存在的墊資、拖欠工程款、肢解工程和非法掛靠、違法分包等行為,行業(yè)管理部門在查處力度上還難以達(dá)到理想的效果,這些行為還沒有得到有效的遏制,市場監(jiān)管缺乏行之有效的措施和手段。 4)臨時用電施工組織設(shè)計。 (4)擬訂項(xiàng)目的組織機(jī)構(gòu)以及項(xiàng)目分包方式,合理安排施工部署。 1)施工組織設(shè)計概論。就現(xiàn)實(shí)情況看,企業(yè)普遍建立有的標(biāo)準(zhǔn)有:施工組織設(shè)計、臨時用電組織設(shè)計、安全生產(chǎn)管理標(biāo)準(zhǔn)、責(zé)任制度等,其中施工組織設(shè)計被廣泛應(yīng)用于企業(yè)內(nèi)部。特別是《建筑安裝工程安全技術(shù)規(guī)程》的頒布,使建筑施工安全技術(shù)工作有章可循。建筑施工生產(chǎn)具有作業(yè)復(fù)雜、流動作業(yè)、手工操作作業(yè)居多、露天施工等特點(diǎn),加之人員施工素質(zhì)、管理方式等因素,整個行業(yè)的安全狀況不容樂觀,施工事故整體上升趨勢,短時間未有明顯改善。旨在于更加全面的做好施工用電的安全管理與事故預(yù)防工作,以提高建筑工地后續(xù)的施工效率和節(jié)約建筑施工成本。關(guān)鍵詞:建筑施工;臨時用電;組織設(shè)計;施工預(yù)算Abstract Building engineering construction is the basic condition of leveling, namely, grading, road, electric flux, water power supplies to the architectural engineering construction site is solving the problem of the construction site of the electricity, the power supply can guarantee, directly affect the construction quality, progress, safety. Construction site temporary electricity design content is based on analyzing the current situation of construction safety and construction site specific problems of the power of the results of the analysis, the main contents include temporary power calculation, the selection of the transformer and distribution system design, as well as safety protection, safety measures and construction drawing design and budget pilation, etc. In addition, in accordance with the relevant regulations, seriously calculation analysis was carried out on the live load, equipment, facilities, switch to be carefully selected and formulated the safe electrical fire prevention measures, technical measures and also increased the relevant equipment installation requirements, the preparation of the lightning protection measures and contents of safety management. Aims to more prehensive utilization work in the construction of safety management and accident prevention work, in order to improve the efficiency of subsequent construction site construction and save construction cost.Key words:Construction;Temporary electricity;Organizational design;construction budget目 錄摘 要 1Abstract 2第一章 引 言 5 5 6 7 8第二章 建筑施工用電安全分析 9 9 10 11第三章 臨時用電組織設(shè)計 13 13 13 13 14 28 30 30 30 31 31 33 33 3開關(guān)箱使用操作順序 35 35 35 36 36 36 37 38第四章 施工圖設(shè)計及預(yù)算書編制 38 38 38 43 43總 結(jié) 46參考文獻(xiàn): 47致 謝 48附錄A 49附錄B 50第一章 引 言 隨著我國GDP連年的持續(xù)快速的發(fā)展,以及加入世貿(mào)組織與申奧、申博成功等新發(fā)展機(jī)遇的催動,尤其是“十一五”規(guī)劃以來,我國基礎(chǔ)設(shè)施和工程建設(shè)的規(guī)模逐年擴(kuò)大,建筑業(yè)發(fā)展日益劇增。根據(jù)統(tǒng)計:2005年發(fā)生846起、死亡987人,重傷296人;2006發(fā)生1004起、死亡1045人、重傷296人;2002年發(fā)生1208起、死亡1292人;2007年發(fā)生1292起、死亡1525人;2008年發(fā)生1144起、死亡1324人;2009年發(fā)生1015起、死亡1193人。改革開放以來,我國的標(biāo)準(zhǔn)化工作進(jìn)一步發(fā)展,建筑行業(yè)標(biāo)準(zhǔn)也在這一標(biāo)準(zhǔn)化進(jìn)程中得到了較大的發(fā)展。 文明施工。施工組織設(shè)計是指對即將擬建的工程項(xiàng)目,在開工前針對工程本身的特點(diǎn)和工地具體情況,按照工程的要求對所需要的施工勞力、施工材料、施工機(jī)具和施工臨時設(shè)施,經(jīng)過科學(xué)計算、精心比較及合理安排后編制出的一套在時間上和空間上進(jìn)行合理施工的戰(zhàn)略部署文件。 (5)擬定施工方案,進(jìn)行技術(shù)經(jīng)濟(jì)比較并選擇最優(yōu)施工方案。臨時用電施工組織設(shè)計是工程施工組織設(shè)計中的一部分內(nèi)容,是建筑施工工地有關(guān)用電方面的總體概況說明與技術(shù)資料,其內(nèi)容包括有:(1)現(xiàn)場勘察;(2)確定電源進(jìn)線及配電箱的位置及線路走向;(3)進(jìn)行負(fù)荷計算;(4)選擇變壓器容量、導(dǎo)線截面積和用電設(shè)備類型、規(guī)格;(5)繪制電氣施工圖;(6)制定安全用電技術(shù)措施和電氣防火措施。不良的市場環(huán)境勢必影響安全生產(chǎn)管理,主要表現(xiàn)在一些安全生產(chǎn)制度、管理措施難以在施工現(xiàn)場落實(shí),安全生產(chǎn)責(zé)任制形同虛設(shè),總承包企業(yè)與分承包企業(yè)在現(xiàn)場管理上缺乏相互配合合作的機(jī)制,現(xiàn)場的安全設(shè)施往往由于配合合作不協(xié)調(diào)招至損壞,給安全生產(chǎn)留下隱患和難以預(yù)測的后果。大量安全事故調(diào)查分析表明,務(wù)工者進(jìn)場施工不久就發(fā)生安全事故的比率越來越高,這一現(xiàn)象充分說明由于缺乏安全生產(chǎn)知識和自我防護(hù)意識已是造成安全事故的重要原因?,F(xiàn)場的項(xiàng)目部沒有按總承包的要求,落實(shí)現(xiàn)場電工的工作責(zé)任范圍,使一些分包項(xiàng)目施工中的違規(guī)違章用電,未能及時得到有效制止。對于國家安全生產(chǎn)監(jiān)管,中央政府的監(jiān)督手段主要為:法律政策和行政政策,并通過各級政府和安監(jiān)機(jī)構(gòu)加以落實(shí)。嚴(yán)格執(zhí)行國家法律、規(guī)范所要求的工程施工內(nèi)容及行業(yè)標(biāo)準(zhǔn)內(nèi)容。另一方面,要求建立健全企業(yè)中的各項(xiàng)制度。⑷合理安排施工工序,可能對路面造成污染的附屬工序要提前進(jìn)行或采取相應(yīng)的保護(hù)措施,有礙于層間結(jié)合的工序不準(zhǔn)在路面上施工或堆放材料。第三章 臨時用電組織設(shè)計 該工程總建筑面積192,800m2,分四棟主體樓,其中三棟每棟27層,另一棟33層,是新建工程。;;;。 則 選擇電容器型號為:,額定容量,額定電容。 (2)防護(hù)要求:配電箱、開關(guān)箱外型結(jié)構(gòu)應(yīng)能防雨、防塵。配電箱、開關(guān)箱周圍應(yīng)有足夠2人同時工作的空間和通道,不得堆放任何妨礙操作、維修的物品,不得有灌木、雜草。 (1)在施工現(xiàn)場專用變壓器的供電的TNS接零保護(hù)系統(tǒng)中,電氣設(shè)備的金屬外殼必須與保護(hù)零線連接。 三相四線供電時局部TNS接零保護(hù)系統(tǒng)保護(hù)零線引出示意1―NPE線重復(fù)接地;2―PE線重復(fù)接地;LLL3―相線;N―工作零線;PE―保護(hù)零線;DK―總電源隔離開關(guān);RCD―總漏電保護(hù)器(兼有短路、過載、漏電保護(hù)功能的漏電斷路器) (3)施工現(xiàn)場的臨時用電電力系統(tǒng)嚴(yán)禁利用大地做相線或零線。機(jī)械設(shè)備必須執(zhí)行工作接地和重復(fù)接地的保護(hù)措施。配電盤或配電線路維修時,應(yīng)掛